New Creative Arts Building
Last updated on April 28, 2026
PROJECT DESCRIPTION:
New Creative Arts Building, Renovate A8 for Creative Arts, Remove A9 and Update Utilities and Systems at A1, A2, A3, Baldwin and Flint Garage.
STATUS:
Active
BUDGET:
$44,332,887
PHASE:
Design
PROJECT SCHEDULE:
Program Validation
August 2025 - January 2026
Schematic Design
January 2026 - February 2026
Cost Trend Check
February 2026 - March 2026
Design Development
March 2026